ODOT District 5 UPDATE 05-20-2021 State Route 204 Resurfacing and Harmon Rd turn lane additions

sr 204 image

State Route 204 update:

Per our inquiry to ODOT regarding the schedule for milling and surfacing/striping in the State Route 204 corridor:

  • Milling and intermediate surfacing have begun between the bridge just east of Ault Road and State Route 256. 
  • The week of May 24, ODOT will transition to night paving on the heavy traffic areas by 256 and the Taylor Road ramp/extension off of Interstate 70. They will stay on nights until milling and base surfacing are completed in these heavy traffic areas, and then transition back to days to perform the final surfacing.
  • The estimated time for paving and related work for the remainder of this project from today is 3-4 weeks, weather permitting.

We will provide an update should this schedule change in a significant way.

We wish to thank everyone for their patience, courtesy and safe travels through the construction zone. Dedicate your full attention to the roadway. Work zones aren’t there to personally inconvenience you. They’re necessary to improve the roads for everyone, and make sure all commuters and workers return home to their families and loved ones.